La Cabana BRC Renovation
Welcome to the La Cabana Beach & Racquet Club Renovation News Link

Updated Renovation Schedule

update

August 28, 2010

Lobby Renovation

We are thrilled to announce that the Lobby renovation started August 23rd, 2010.

It was a memorable occasion when General Manager Mr. Joe Najjar and President of the Board Mr. Willie Mosconi grabbed a jackhammer and chipped the first lobby boulder, as the demolition of the old indoor waterfall began, signaling the upcoming, much anticipated lobby renovation.

The new lobby will feature a state of the art glass elevator and a new staircase, a modern front desk, beautiful glass artwork and more. This project also includes a new porter cochere and new aluminum window frames and is scheduled to be completed in approximately 5 months.

A temporary Front Desk has been set up and is located next to the Minimarket.

Please excuse our appearance as we enhance your home-away-from-home for your enjoyment. Mo<

February 17, 2010

Renovation is in full swing and on schedule

You will be pleased to know that we have successfully completed phase 6 and immediately started with phase 7 during the 1st week of January, 2010 and should be ready for use by the end of April, 2010. This places us over 50% of the total renovation project.

With the start of phase 7 the General Contractor construction staging area was moved to the north side of the Resort. The fencing has also been moved, giving access to all patios for the Sunday to Sunday ground floor units. Although without a beautiful landscaping at the moment, the owners still enjoyed being able to sit outside on their patios again.

The fencing is now blocking the access to all patios for the Saturday to Saturday ground floor units to allow the traffic of heavy equipment. Contrary to the Sunday to Sunday section that had to wait until the whole Sunday section was completed, these fences will be gradually removed as soon as each phase is completed.

Unfortunately, we had to block off the complete access to patios of the ground floor Ocean Front units, 145E & 146E, for safety reasons. These patios will become available again by the end of October, 2010. We thank you for your understanding for any inconvenience this may cause.

Going back to the topic of the landscaping, before going over to re-do the landscaping and since we think that this is the right moment to do this, we have approached an expert on that field to redesign the whole area. We are very excited for the final results and will keep you posted.

On a different note, the Board of Directors has approved to start changing the balcony railings as of phase 7 and on.

October 30th, 2009

New photos taken from the middle of the resort show the renovation progress begin made.

September 29th, 2009

POOL ACCESS RESTRICTION

The ongoing renovation has reached Phase 6, which marks the midway point of the 12-phase project at the Resort.

Phase 6 renovations will affect some areas that have access to and from the pool area. As a result, we have extended the passageway for construction vehicles and material transport to include all “26” room numbers.

As a requirement of the project’s safety codes, we have closed the south lobby landing exit to the pool area and the main walkway between the activities center and the game room. Owners and guests can only access the pool area, bar and restaurants via the north lobby landing. To help you navigate your way around the construction area, we have put up signage to direct you through these areas.

We apologize for the inconvenience that this phase of the renovation may cause. We understand that the new route via the north lobby landing requires a bit more walking to access your favorite places at the Resort. Please keep in mind this new route is for your own safety and protection while we enhance and upgrade your “home away from home.”

Phase 6 is the last part of the renovation that restricts patio use on the ground floor for Sunday to Sunday units. This section will be reopened by the second week of January 2010 and owners will have access to their patios as well as the south lobby landing exit and main passageway to the pool area.

As we move to Phases 7-9, which encompasses the Saturday to Saturday units, the construction staging area will move to the north side of the Resort. With the start of Phase 7, all Saturday to Saturday ground floor units will not have access to their patios. When reaching phase 8 and 9, gradually the construction fence and passage way is moved from phase 7 and on to allow owners and guests access to the patios of those the ground floor units that are completed.

We thank you for your cooperation during the renovation project. If you need any additional information, please feel free to contact us.

Archi


July 24th, 2009

MORE ENHANCEMENTS

While we are moving on with the replacement of the corridor tiles in the area of the renovated rooms, we are approaching the area of the lobby landings. During this process we will be enhancing the lobby landings as well. This entails removal of the existing tiles and replacing these. This is not a pretty sight at this moment but the end result is worthwhile the waiting for; not only for the new look but for safety as well since we will be placing nice anti-slip tiles.

Photo 1 | Photo 2


July 13th, 2009

RENOVATION UPDATE – PHASE 5 HAS STARTED

The renovations project is moving along nicely with the completion of Phase 4 and the recent stripping of 28 rooms to start Phase 5. Units 114A, 214A, 314A and 414A will be out of commission for weeks 26 through 37 with an expected completion date of Sept. 20, 2009. During weeks 26 through 38, units 116ABC, 216ABC, 316ABC, 416ABC, 118 ABC, 218 ABC, 318ABC and 418ABC undergo renovation and are expected to be completed by Sept. 27, 2009.

Phase 6, which consists of 40 rooms, is scheduled to start on Sept. 27, 2009 and will continue over the course of weeks 39 to 51 (expected completion Dec. 27, 2009) impacting units 120ABC, 220ABC, 320ABC, 420A, 122ABC, 222ABC, 322ABC and 422ABC. During weeks 39 through 52 (Sept. 27, 2009 – Jan. 3, 2010), units 124ABC, 224ABC and 424ABC will be renovated. From Oct. 3, 2009 through Jan. 9, 2010 (weeks 40 -1), units 226BC, 326 BC and 426BC will remodeled.

As a reminder for Sunday check-ins, as the renovated units of Phases 3, 4, 5 and 6 (located poolside on the ground level) become available for occupancy, the patios of these units will not be accessible. This area will be fenced off for the safety of all guests. This will be in effect until the end of December 2009 when we anticipate the re-opening of the patios.

Photo 1 | Photo 2 | Photo 3 | Photo 4 | Photo 5 |


Updated Renovation Schedule

April 1, 2009

RENOVATION UPDATE

Information on renovated pool side ground level units

Information on renovated pool side ground level units In keeping you up to date on the progress of the renovation project, we would like to advise owners of renovated ground floor units with a Sunday or Saturday check-in pattern, of the following:

Sunday check-in day: As the renovated units of Phases 3, 4, 5, & 6 located pool-side on the ground floor level become available for occupancy, the patios of these units will not be accessible. This will be in effect until the end of December 2009 and for construction safety this area will be fenced off.

Saturday check-in day: As the renovated units of Phases 7, 8, & 9 take place through end of 2010, patios affected by these phases will also not be accessible as noted above. In the case of the Saturday units, once phase 7 is completed and construction moves to phase 8, the patios of the units in phase 7 will become available for use. This will be the case also when construction moves to phase 9 that will then make the patios of phase 8 available. For phase 10 and on we will give an update based on the approved location of the construction staging area in due time.

This inconvenience is due to safety issues plus to remain in compliance with our security codes and insurance requirements. We thank you for your understanding and cooperation.

IMPORTANT:
REVISED RENOVATION SCHEDULE-MARCH
REVISED DATES PHASE 4 - 12

March, 2009

RENOVATION SCHEDULE REVISED

The renovation project is going its way and not without challenges. Last December it was recommended to the Board of Directors that the chilled and hot water pipes needed to be replaced due to the risk of having to go back later for repair or replacement with consequences of damage to the new rooms. This was not part of the scope of work for the general contractor nor was there consideration taken for the additional time frame needed for these replacements. The Board has contracted another company to replace these pipes. The general contractor had to wait for this new company to finish replacing the pipes before they could close up the walls. This situation created a delay in the delivery of the units of Phase 3 and consequently moved the schedule of Phase 4 that could not be stripped for renovation due to the fact that most of these units were used to relocate those owners that could not occupy Phase 3. These water pipes run vertically through the building. Due to this situation, the units of phase 4 through phase 12 will undergo renovation from the 4th floor going down to the 1st floor as well as their delivery when completed for occupancy. Please review this newly updated renovation schedule below before making any travel arrangements to La Cabana and if in doubt with your travel dates, please communicate by e-mail owners@lacabanabrc.com

We apologize for this inconvenience but this important decision had to be made to safeguard your renovation investment.

IMPORTANT:
REVISED RENOVATION SCHEDULE-MARCH
REVISED DATES PHASE 4 - 12

IMPORTANTE:
Horario actualizado de la renovación
Plan de renovación fase 4 hasta 12

Dear Members,

With a Renovation project of this scope comes some inconvenience, so in an effort to make the process as hassle-free as possible we're reminding you of the two options available if your unit is affected by the renovation.

Deposit your week with Interval International. You can contact Interval International directly by calling 1-800-828-8200 or 1-305-666-1884 or visiting the company's website at www.intervalworld.com.

Accept an Entitlement Certificate, that entitles you to a one-week stay (or multiple weeks for those who own multiple weeks) and which is valid for five (5) years from the start date of your week that was scheduled for renovation. The Entitlement Certificate replaces the week(s) that you were not able to use due to the renovation and enables you to return to your home Resort at any time based on availability. If you decide to send a guest in your place using the Certificate, you will still need to fill out the usual 'GUEST Authorization' form. To request any of the two above-mentioned options, owners must comply with their yearly financial responsibilities to the Cooperative Association (including maintenance fees and the renovation special assessment). If your unit is affected and you make travel arrangements before you speak with us, your unit will not be available - and we'll be unable to accommodate you.

IF YOU HAVE NOT ALREADY DONE SO: We urge you to respond by e-mail to owners@lacabanabrc.com or by fax at 011-297-587-1483 as to which of the two options you prefer.

Thank you for your understanding and cooperation as we try to accommodate all of our valued owners. We will continue to keep you updated on the renovation project, and we hope you share our enthusiasm for the future of our revitalized resort in the tropics. Please feel free to contact us if you have any questions, concerns or comments.

Sincerely,

The Management Team
La Cabana Beach & Racquet Club


ARCHIVED RENOVATION NEWS

December 12, 2008

The mentioned due date of December 15, 2008 on the bottom part of the Maintenance Fee invoice, is only applicable for the 2009 Maintenance Fee. The due date for the 2009 Renovation fee (Special Assessment) remains April 1st 2009, and the 2010 Renovation Assessment due date remains April 1st 2010.

In the event the owner wishes to deposit or exchange their week with Interval International or rent out their week, the renovation assessment for that particular year has to be paid in advance. In the event the owner wishes to sell their timeshare, the total amount for renovation assessment and maintenance fee has to be paid in full.

La fecha límite señalada del 15 de diciembre de 2008 que aparece en la parte baja de la factura de la Cuota de Mantenimiento, es únicamente aplicable para la Cuota de Mantenimiento del 2009. La fecha límite para la cuota de Renovación del 2009 (Cuota Extraordinaria) se mantiene para el 1 de abril de 2009, y la fecha límite para la Cuota de Renovación se mantiene para el 1 de abril del 2010.


September 11, 2008

The units of phase 1 have been completed and are now being occupied. The stripping of the rooms in Phase 2 was done while the demolition works is in its final stages.

Photo 1 | Photo 2 | Photo 3 | Photo 4 | Photo 5 | Photo 6 | Photo 7 | Photo 8 | Photo 9 | Photo 10

The photos below show the final room product:

Photo 1 | Photo 2 | Photo 3 | Photo 4 | Photo 5 | Photo 6 | Photo 7 | Photo 8 | Photo 9 | Photo 10 | Photo 11 | Photo 12 | Photo 13 | Photo 14 | Photo 15 | Photo 16 | Photo 17 | Photo 18 | Photo 19 | Photo 20 | Photo 21


May 30, 2008 Update

Photos of renovations on Block 1. Date of completion is scheduled for August 5, 2008.

Photo 1 | Photo 2 | Photo 3 | Photo 4 | Photo 5 | Photo 6 | Photo 7
Photo 8 | Photo 9 | Photo 10 | Photo 11 | Photo 12 | Photo 13 | Photo 14

May 13, 2008 Update

The room renovation project officially started May 1st, 2008! We will be keeping the membership updated as to the progress of this enormous undertaking through our website, our printed newsletter “Highlights” as well as our e-mail newsletter “Happenings”. To start with, we are able to supply you with an update on the Renovation Assessment collection.

To date, 45% of the total renovation assessment remains to be collected.

We would like to remind those owners that have opted for the three year payment plan and only paid the first term now, not to forget that you are still responsible for the balance. Either to pay the remainder balance between now and April 1st, 2009 or pay the second and last term as scheduled by due dates of April 1st, 2009 and April 1st, 2010.



May 7, 2008 Update
We have great news to report – the room renovation officially started on May 1, 2008! The project we’ve embarked on will substantially enhance your future vacation experience at La Cabana Beach & Racquet Club, so we’d like to take this opportunity to thank you once again for your understanding and compliance as we proceed with our twenty-first century ‘renaissance.’

One of the questions on all your minds is ‘Who was awarded the General Contractor bid for the renovation?’ Here’s your answer: Konstruktiva & Design N.V., a local contractor who has quite a bit of experience with similar projects in Aruba, and we’re confident they’ll do an excellent job re-shaping our ‘home away from home.’
The first phase of the renovation began on May 1st whereby for three days a crew of designated La Cabana Beach & Racquet Club associates completely stripped 36 rooms of all furnishings, bedding, etc. The three-day process of stripping the rooms entailed saving many items that we will use as replacements if needed in the balance of the rooms awaiting to be renovated. The rest of the old furniture and appliances have been stored in containers for sale first to La Cabana Beach & Racquet Club associates and then to the local market.

Since May 1st and May 2nd were holidays in Aruba, the general contractor officially began work in the rooms on Monday, May 5th. To reiterate from previous correspondence, the Board approved the pre-purchase of time-sensitive materials such as tiles, cabinetry, granite tops and light fixtures for the first two phases of the project in an effort to avoid any delay in the renovation process. Each phase should take about 14 weeks to be completed.
Safety is of paramount importance, so to avoid public access to the work space the general contractor has already sectioned-off the construction area. Keep in mind that the mesh blocking the construction area is only temporary, and that while the renovation process itself isn’t always attractive, the final result will be well worth it.

To ensure that the renovation remains on schedule and runs smoothly, the Board of Directors has hired a project management company, BK Consultants, who will have a full-time person in Aruba to supervise and monitor the efforts of the general contractor. This project manager will also act as a liaison with the management team regarding any operational, financial or engineering matters that may arise.
We are finalizing contacting owners in the second block whose units will be affected by the renovation and soon will be contacting owners in the 3rd phase. Please keep in mind that many owners whose units undergo renovation during their owned week will be offered the Entitlement Certificate. This certificate is valid for five (5) years from the start date of their week that was scheduled for renovation. If the owner decides to send a guest in their place using the certificate, the owner will still need to fill out the usual ‘Guest Authorization’ form.

With the renovation in mind, it’s imperative that you keep us updated with changes to your contact information such as a new address, phone number or e-mail address. Communication between our staff and our valued owners is vital to the workings of our operation. If we don’t have your proper phone number, problems might be encountered with the use of your room. The last thing we want is for your stay in paradise to be stressful! So, when informing your friends and relatives about your new contact information, please make sure La Cabana BRC is also on your list of ‘people to tell.’
We will continue to keep you updated right here on the renovation project. We hope you share our enthusiasm for the future of our revitalized resort in the tropics.

This special Web link is your Renovation News Center devoted to providing all our Beach & Racquet Club owners with the full project details including:

This Web link will enable you to see the step-by-step development and progress of your Resort’s renovation.

This link will keep you informed 24/7 about the status of this exciting project and enable you to reach us easily and conveniently

Note:The Model Rooms are available for viewing on Wednesdays at 11:15 am, just after the Owners Meeting.

THE RENOVATION

Some questions have arisen about the planned renovation, many of which have been answered in weekly owners meetings or individual discussions. Nevertheless, we would like to use this forum to ensure that every owner fully understands the plans, the process and the results of what will make our vacation home, not only beautiful, but also increase the value of your vacation investment.

Two of the re-occurring questions raised are how we came up with the assessment and why is it so expensive.

First, let us assure you that every dollar being spent is being done with a fine-tuned focus on saving money. However, we are not sacrificing quality to achieve this. It is important that we plan and renovate with the best quality products to protect your interests, future and long-term value of your units. This comes with a price tag.

The Process

Now, how did we arrive at the actual assessment? We all recognize the need for this renovation. Over the past several years, we have upgraded and changed furniture piece by piece in order to provide basic maintenance of our units. However, such upkeep has proven not to be cost effective.

Following feedback from our owners meetings, email correspondence and direct communication with the Board of Directors, we launched a research and planning project with architects, engineers and designers in which they have provided us with a detailed plan as well as estimated costs for the renovation – all designed to protect your interests and ensure the sustained value of your units.

The Costs (online payment form is now available).
Early Payment Discount Schedule (if paid by April 1, 2008)

The cost of doing business in Aruba is far more expensive than doing business in North America. Everything we do involves purchasing and bringing in supplies that do not exist on Aruba. This means shipping and freight costs that are higher than our U.S.-based counterparts. This also results in Aruba customs, import duties and BBO taxes that add to the cost.

We also have high insurance costs associated with any building project. And finally, we have the labor costs applicable to Aruba. These collective costs mount up. A major renovation, as the one proposed, will result in high costs for the supplies plus the aforementioned associated costs that may not be included in a comparable U.S. project.

All of the above costs are calculated in the assessment that you have received for payment of the planned major renovation.

The Plans

We are doing these Model Rooms taking everything into consideration, but not limited to the cost, your comfort and the general esthetics of the unit.

These Model Rooms will enable us to ensure that we are doing it right before we proceed with the mass renovation of all the units.

Many of our owners have called, e-mailed and asked us about the extent of their unit renovation. Please note that final inclusion of certain furniture, appliances and accessories as well as changes in floor plan will be made after completion of the two Model Rooms.

The following is the proposed list of items that will give you an idea of what is being replaced in your unit.

  1. Floor tiles in the entire unit, baseboards, new wall texture, new front doors.
  2. Living and dining room furniture, television (with a flat screen TV), lamps, artwork, wall lightning, ceiling fans, soft goods and draperies.
  3. Kitchen sink, counter tops, cabinets, appliances, cutlery, silverware, china, pots and pans.
  4. Complete bathroom renovation with new basin, vanity, toilet, shower, mirror and light fixtures.
  5. All bedroom furniture, television (another flat screen TV), artwork, bedspreads, soft goods and draperies.
  6. Air conditioning unit relocation.

The Why

Once again, these renovations have been long overdue. The Beach and Racquet Club is 17 years old this year and our units have become tired. The renovation will not only bring the resort back to life, it will revitalize the individual units raising the value of your unit and the resale value as well. Additionally, this renovation will guarantee our five (5) star exchange status and increase the corresponding exchange power.

This will be the first full renovation in the 17-year existence of the resort. We are going beyond a cosmetic cleansing. We are upgrading both the look and feel of the resort and adding new appliances, new lighting, new amenities and much more.

Saving Money and Doing It Right

The Model Rooms will save us time, energy and money in the end. The exercise in producing renovated sample units (Model Rooms) is necessary to ensure that we do this right the first time. By creating the Model Rooms we will have gone through the process, re-evaluated, corrected and fine-tuned the models before we proceed with the major renovation of all the units.

The Communication

What started as discussions in the Board Meetings spilled out into the Members Lounge and over the Internet in our Owners Chat Rooms, at poolside and on the beach. Everyone has been talking about these renovations for more than a year now.

While we have reached out to as many people as possible, it is virtually impossible to reach and communicate with everyone.

Board members have had numerous conversations in person and over the Internet with owners about these plans. Comments have been made, suggestions offered and everyone who has wanted to say something has been heard.

There is an old saying that when God started out to build a horse he decided to turn the task over to a committee. The result was a camel. We don’t want any humps in our resort so we are not going to be able to accept every suggestion. That would be impossible and we would end up with very strange rooms. Rather, we will review all comments and try to blend as much as feasible into the final plan.

The Assessment

When we sent out the convocation last month announcing the Annual General Meeting we did not specify the Assessment Fee’s due date. Please refer to the updated and recently posted “Renovation Assessment Schedule and Due Dates”. Stay tuned, we will keep you informed of everything, every step of the way. This is your vacation home and we intend to make it the best there is for you, your family and every other owner.

Assessment Fee

YOUR OMBUDSMAN (Official appointed to act as a go-between)

We want you to use this Web link to communicate your thoughts and ideas about the Beach & Racquet Club renovations and be sure to embrace the knowledge of your very own “Archi Tech” who will guide you through the modernization process.

“Archi Tech,” the Renovation coordinator, is your very own special ombudsman who will help you understand the renovations issues and share your ideas with the Co-op Association Board of Directors.

You can click on “Archi Tech” at any time you have questions or comments about the next phase of the Beach & Racquet Club’s development. “Archi Tech” will respond in a timely manner and promises to be helpful at all times. He is a renovations specialist and is there to help you.

Archi

MEMBERS E-MAIL

Please remember, both “Archi Tech” and this Web link will keep you up to date on the renovation progress 24/7. Log on at any time and you will find the latest news, updates and links to everything under the Renovations umbrella. You can also reach us by e-mail.

We promise you that when the project is finished, the value of your vacation home in Aruba will be as outstanding as the facilities themselves.

Let’s toast to the next phase of the La Cabana Beach & Racquet Club!